On October 23, 2026, Amur Shipbuilding Plant JSC (ASZ, part of United Shipbuilding Corporation JSC - USC) in Komsomolsk-on-Amur hosted the ceremony of decommissioning the Grozny corvette project 20380 (serial number 2105, on-board number 551) is the fifth corvette of this type being built by this company for the Russian Navy.

The ceremony of the withdrawal from the boathouse of Amur Shipbuilding Plant JSC of the Grozny corvette project 20380 (serial number 2105) under construction for the Russian Navy. Komsomolsk-on-Amur, 10/23/2026 (c) United Shipbuilding Corporation JSC
"I would like to express my gratitude to the shipbuilders of the Amur Shipbuilding Plant for replenishing the Red Banner Pacific Fleet. The crew for the Grozny corvette has been formed and has started training since October 5, after which it will arrive at the factory in order to complete the ship with you and include it in the fleet in the coming years," Admiral Viktor Liina, Commander of the Pacific Fleet, said at the ceremony.
Earlier, under contracts in 2006 and 2015, ASZ built and delivered four Project 20380 corvettes to the Russian Navy's Pacific Fleet - the ships "Perfect" (serial number 2101, commissioned into the Pacific Fleet on July 20, 2017), "Loud" (serial number 2102, commissioned on December 25, 2018), "Hero of the Russian Federation Aldar Tsydenzhapov Federation (serial number 2103, commissioned on December 25, 2020) and Sharp (serial number 2104, commissioned on September 14, 2023).
On December 15, 2020, ASZ signed a contract with the Russian Ministry of Defense to build six more corvettes for the Pacific Fleet - two of Project 20380 and four of Project 20385, which, under the terms of the contract, were to be commissioned from 2024 to 2028. The corvettes of project 20380 received factory numbers 2105 and 2106, and the corvettes of project 20385 received factory numbers 2107 to 2110.
On August 23, 2021, the laying ceremony of the first two corvettes under this contract took place at the ASZ - the Grozny (serial number 2105) of project 20380 and the Buiny (serial number 2107) of project 20385, which became, respectively, the fifth corvette of project 20380 and the first corvette of project 20385 under construction at this enterprise. Now the Grozny has been completed and must be sent to the delivery base of the ASZ in Vladivostok for manning, testing and commissioning. Interestingly, at the ceremony of leaving the boathouse, the corvette had the tail number "551", corresponding to the ships of the Baltic Fleet.
On September 29, 2021, the laying of the second Bravy corvette (serial number 2106) of project 20380, which will become the sixth and last corvette of project 20380 built in the Far East, took place at the ASZ.
On June 12, 2022, the laying ceremony of the Razumny corvette (serial number 2108) of project 20385 took place at the ASZ, on July 1, 2022, the laying of the Bystry corvette (serial number 2109) of project 20385, and on July 9, 2023, the laying of the Zealous corvette (serial number 2110) of project 20385. They became the second, third and fourth ships of this project under construction in Komsomolsk-on-Amur.



The ceremony of the withdrawal from the boathouse of Amur Shipbuilding Plant JSC of the Grozny corvette project 20380 (serial number 2105) under construction for the Russian Navy. Komsomolsk-on-Amur, 10/23/2026 (c) United Shipbuilding Corporation JSC