The US Navy is counting on a new funding model to accelerate the modernization of the submarine fleet

1376
0
0

Image source: topwar.ru

In 2021, the submarines of the US Navy stood for a total of 1,100 days. Without functional changes, the combat readiness of the submarine fleet can be reduced to a minimum, according to the US Navy command. After all, now the fleet has twice as many submarines under maintenance than it should be. These boats require three times more unplanned work to bring them into a really combat-ready state.

A change in the situation is possible only if financing of technical measures is established. According to Rear Admiral John Rucker, the US Navy can introduce new practices from 2026.

Rucker said that due to the addition of additional work after the start of maintenance, 30% of the total work on submarines is unplanned. The US Navy is going to reduce the number of unplanned work to 10%, which can be done by improving the planning process.

Separately, the Rear Admiral drew attention to financing the purchase of all necessary materials. Currently, the Navy finances only 40% to 50% of the purchase of materials before the start of maintenance; the remaining amount is ordered after the start of work. But such a financing system is also fraught with numerous problems.

By fiscal year 2026, the Navy will strive to have 90% to 95% of all materials available. The problem of earlier purchase of materials becomes even more acute due to the increased delivery time. Today, the Navy has few spare parts for the newer Virginia-class boats.

"We have to distribute the money in a different way. Our model doesn't work because it was built on the assumption that everything was 20 or 30 years ago when we had three times as many suppliers

- noted Rear Admiral Rucker.

The command of the US Navy has repeatedly called submarine forces one of America's main advantages over such opponents as China and Russia. The US has 50 attack submarines, which is quite small compared to the need for 66-72 attack submarines. Moreover, 18 submarines are under maintenance or waiting for their turn.

The rights to this material belong to
The material is placed by the copyright holder in the public domain
  • The news mentions
Do you want to leave a comment? Register and/or Log in
ПОДПИСКА НА НОВОСТИ
Ежедневная рассылка новостей ВПК на электронный почтовый ящик
  • Discussion
    Update
  • 02.05 00:02
  • 0
Комментарии к "В ВСУ допустили сценарий российского ядерного удара" и "На Западе обсуждают слова замкомандующего ВС ВСУ об опасности применения ТЯО РФ"
  • 01.05 21:30
  • 15650
Without carrot and stick. Russia has deprived America of its usual levers of influence
  • 01.05 18:56
  • 0
Комментарии к "На Украине заявили о применении «Ковра» российского Су-57" и к "В США объяснили появление «Ковра» у российского Су-57"
  • 01.05 18:06
  • 0
Комментарии к "В США констатировали исчезновение Су-57" и к "В США предложили «спасение» для российского ПАК ДА"
  • 01.05 15:00
  • 31
Putin will be able to send military personnel to protect compatriots from arrest abroad (The Times, UK)
  • 01.05 10:17
  • 5
Russia's economy predicted tectonic changes in 10 years
  • 01.05 09:58
  • 1116
Подушка безопасности Ирана на фоне слов Израиля о недостаточности вывоза урана
  • 01.05 07:21
  • 6
Новейший российский «Союз-5» впервые запустят 2 апреля
  • 01.05 04:47
  • 0
Комментарий к "«Потешная флотилия». Европа создает новый военный альянс против России"
  • 01.05 03:46
  • 0
Комментарий к "Конфликт в Персидском заливе показал эффективность российской системы ПВО"
  • 01.05 02:08
  • 1
"Funny flotilla." Europe is creating a new military alliance against Russia
  • 01.05 01:58
  • 1
Artificial intelligence on the battlefield
  • 30.04 23:53
  • 0
Комментарий к "Высокотехнологичные подводные лодки Путина бросают вызов НАТО в глубинах Атлантики (Bloomberg, США)"
  • 30.04 17:37
  • 0
Комментарий к "Названо наводящее ужас на ВСУ в тылу российское оружие"
  • 30.04 14:49
  • 1
НПЦ «ЭЛВИС» сорвал сроки разработки российского микропроцессора на замену микросхем Texas Instruments — компанию оштрафовали