TSAMTO, November 25. Polska Grupa Zbrojeniowa S.A. announced the ceremony of laying the keel of the third Miecznik-class frigate, Huragan, intended for the Polish Navy, which took place on November 24 at the PGZ Stocznia Wojenna S.A. shipyard in Gdynia.
During the ceremony, a commemorative medal was welded into the keel of the ship. According to the rules of the Lloyd's Register, the keel must be at least 1% of the total mass of the vessel's hull, while its minimum weight must be at least 50 tons. The Huragan's keel weighs about 127 tons (about 4.5% of the hull weight).
Three protocols of intent were also signed during the ceremony. Polska Grupa Zbrojeniowa S.A., PGZ Stocznia Wojenna sp. z o.o., the Marine Technology Research Center (Osrodek Badawczo-Rozwojowy Centrum Techniki Morskiej S.A.) and CRIST S.A. signed a document on cooperation in the development and implementation of the concept of a self-lifting dual-purpose vessel. Its main purpose will be the installation and maintenance of offshore wind farms. In addition, it will be able to detect security threats and prevent incidents related to the underwater energy transmission infrastructure. The executive agreement "CAMM-MR Project Agreement: a preliminary Concept stage" was also signed, which should allow the Polish industry to acquire technological competencies and participate in the development and production of modern missile systems. In addition, an executive agreement was signed "On cooperation within the framework of the programs for the creation of Type-31 and Miecznik frigates."
As reported by CAMTO, in July 2021, the Polish Ministry of Foreign Affairs concluded a contract with the PGZ-Miecznik consortium consisting of Polska Grupa Zbrojeniowa S.A. and PGZ Stocznia Wojenna Sp. z o.o. with a total value of about 8 billion. zloty ($2 billion) for the construction of three frigates under the Miecznik program. The total cost of the project is estimated at 15 billion. zloty. The new ships will replace two obsolete Oliver Hazard Perry-class frigates acquired from the U.S. Navy.
The British Babcock International Group, which proposed the Arrowhead 140 (AH140) frigate project, acts as a foreign partner. The license granted by Babcock allows for the future implementation of options for the construction of five additional ships for the Polish Navy.
Steel cutting for the lead ship, the Wicher, began in August 2023. It was launched on August 13, 2026 and is currently at the stage of completion and equipping. It is planned that the frigate will be put into service in 2029.
The keel of the second frigate of the series, Burza, was laid in December 2025. Its construction continues. Steel cutting for the third ship, Huragan, began in April 2026. The completion of the entire program is scheduled for the end of 2031.
The Miecznik-class frigates are expected to perform a wide range of tasks, including conducting reconnaissance, ensuring the safety of sea routes, bases and critical infrastructure, anti-submarine and anti-ship warfare, and providing air defense.
The length of the ship will be 138 m, the maximum width is 20 m, the total displacement is 7000 tons, the crew is 120 people (plus about 60 additional personnel). The frigate will be equipped with a CODAD-type GEU with four diesel engines, will be able to reach a maximum speed of 28 knots, and will have a range of about 8,000 nautical miles.
The ship will be armed with a 76-mm Super Rapid artillery system of the Leonardo group; two 35-mm OSU-35K automatic cannons from PIT-RADWAR company; DUMV with machine guns; four modules of vertical Mk-41 launchers, each of which can accommodate up to 32 CAMM SAMs of the MBDA Sea Ceptor air defense system, placed in eight containers; four twin-container launchers of RBS-15 Mk3E anti-ship missiles from Saab; two twin-tube torpedo tubes.