"Problems with hearing loss have been solved": the crews of the British Ajax BMP are given new headphones

2160
0
0

Image source: topwar.ru

In Britain, the epic with the new Ajax BMP has been going on for 12 years, 5.5 billion pounds have been spent on the program for the creation of which. 414 vehicle hulls have already been built, and 116 towers are ready for installation after the tests are completed – their completion is just around the corner, says Defense Minister Ben Wallace.

In total, 589 infantry fighting vehicles for various purposes were promised to the army, the first of which were to enter service in 2019, but the project has not yet reached technological maturity.

The problems accompanying the program to create a new Ajax armored vehicle have declined. The project is getting back on track after a series of unfortunate setbacks and delays

- the head of the military department told the BBC.

One of the main problems is the excessive level of noise and vibrations, which complicates the operation of the BMP. The crews complained of hearing loss and numbness of the limbs. More than 300 people who took part in the tests were examined, some of them had long-term hearing damage.

In order to avoid excessive vibration, the equipment responsible for manual control was reinstalled and changes were made to the design of the seat mounts.

The noise was reduced thanks to headphones with two-layer hearing protection and a built-in communication system, which began to be issued to soldiers operating equipment. This allowed us to solve the problems with hearing loss

- indicated in the publication.

It is expected that the final stage of testing will last 18 months, but it may take another two years before Ajax finally enters service with the army.

The rights to this material belong to
The material is placed by the copyright holder in the public domain
Do you want to leave a comment? Register and/or Log in
ПОДПИСКА НА НОВОСТИ
Ежедневная рассылка новостей ВПК на электронный почтовый ящик
  • Discussion
    Update
  • 31.07 19:20
Комментарий к "Модернизацию атомного подводного флота назвали важнейшей задачей для развития ВМФ"
  • 31.07 19:02
  • 2
Russia has announced its first destroyer program in 40 years. Urgently needed: Ocean-going warships (Military Watch Magazine, USA)
  • 31.07 18:51
  • 0
Комментарий к "Россия объявила о первой за 40 лет программе создания эсминцев. Срочно требуются: океанские боевые корабли (Military Watch Magazine, США)"
  • 31.07 18:37
  • 16347
Without carrot and stick. Russia has deprived America of its usual levers of influence
  • 31.07 18:09
  • 1
Госкомвоенпром: ОАО "АЛЕВКУРП" усовершенствовало оптико-электронную систему для ЗРК
  • 31.07 18:00
  • 1
Модернизацию атомного подводного флота назвали важнейшей задачей для развития ВМФ
  • 31.07 17:37
  • 1
Sea revenues: The Caspian Flotilla acquired its own aircraft
  • 31.07 17:18
  • 1
Минобороны: Россия обладает опытом создания масштабных группировок ПВО
  • 31.07 07:33
  • 0
Комментарий к "Чем же была более всего сильна промышленность Российской империи"
  • 31.07 05:53
  • 0
Комментарий к "Чего Европе ждать от задуманной США “НАТО 3.0”? (The Spectator, Великобритания)"
  • 31.07 05:08
  • 0
Комментарий к "Могла ли Россия потерпеть поражение в Первой Мировой Войне?"
  • 31.07 01:56
  • 0
Комментарий к "Почему Суворов взял «неприступный» Измаил, имея меньше солдат, чем защитников"
  • 31.07 01:37
  • 1
What can Europe expect from the US-conceived “NATO 3.0”? (The Spectator, UK)
  • 31.07 01:19
  • 1
Болгария подключилась к нефтепроводу НАТО (Дума, Болгария)
  • 31.07 01:15
  • 3
На Украине отмечают рост у ВС РФ количества средств для противодействия Starlink